http://www.ricardo-vargas.com/pmbok5-processes-flow/
Then start preparing the notes as you study from multiple blogs/notes/PMBOK5 and everywhere you can learn from !!
Initiate Process:
Planning Process:
Monitor and Control:
Execute Process:
Closing Process:
- http://edward-designer.com/web/pmp/ where i have learnt and applied many things to consolidate into one blog for my preparation.
1.
Process – a package of inputs, tools and outputs,
there are 47 processes defined by PMI
2.
Phases – a group of logically related activities,
produces one or more deliverables at the end of the phase (maybe with exit
gate/kill point [probably in a sequential relationship])
3.
Phase-to-Phase relationship: There can be one or more phases in projects. Even if you do not
follow standard project management, unconsciously one or a combination of below
three relationships will exist.
1.
Sequential
Relationship – One phase will start only after finishing the previous phase
2.
Overlapping
Relationship – Simultaneously two or more phases will run.
3.
Iterative Relationship
– Phases are not pre-planned. Next phase will be decided and planned based on
the outcome of previous phase
4.
Project – a temporary endeavor to create a unique product, service or
result (or enhancement of existing services/products (e.g v.2 development is a
project) ) as opposed to operation, may hand over the product to operation
teams
5.
Operation manages
process in transforming resources into output
6.
Projects have more
risks and uncertainties than operations and require more planning
7.
Program – a group of coordinated projects, taking operations into
account, maybe with common goals, achieving benefits not realized by running
projects individually, if only the client/technologies/resource are the same,
then the projects should be managed individually instead of a program
8.
Portfolio – group of programs/projects to achieve organizational
strategic goals within the organization/operation management, all investments
of the organization, maximize the value by examining the components of the
portfolio and exclude non-optimal components
9.
Business Value is the total values (tangible and intangible) of the
organization
10.
Organization Strategy may be expressed through mission and vision
11.
Use of
portfolio/program/project management to bridge the gap between organization strategy and business
value realization
12.
Progressive Elaboration (rolling wave planning is one of the methods used in activity planning) – analysis and
estimation can be more accurate and elaborated as the project goes (usually in
phased projects) such that detailed planning can be made at that point.
13.
According to the Project
Management Body of Knowledge (PMBOK), a “project” is a temporary endeavor undertaken to
create a unique product or service.”
14.
Triple constraint- project scope, time and cost
15.
A portfolio is a collection of projects or programs and other work
that are grouped together to facilitate effective management of that work to
meet strategic business objectives.
The projects or programs in the portfolio may not necessarily be interdependent or directly related
16.
A project management office (PMO) is an organizational unit to centralize and coordinate the
management of projects under its domain. A PMO can also be referred to as a
"program management office," "project office," or
"program office." A PMO oversees the management of projects,
programs, or a combination of both
17.
Project management is a set of tools and techniques that
are used to organize the work of the project to help bring about a successful
project.
18.
The contract between the organization and the vendor super cedes all other work related documents
19.
Customers, internal or
external, are the most important stakeholders in
a project
20.
Scope verification must take place at the end of each phase
21.
Money already spent on
a project is called sunk cost and should not be taken into consideration
when determining if a project should continue. Instead, the cost of the work to
complete is one of the elements that should be taken into consideration when considering
to kill a project
22.
Phase end reviews are also called phase exits, phase gates, or kill points.
23.
The project life cycle goes through a series of phases to
create the product
24.
Project managers manage things, but lead people. What's
the difference?
Management is the process of getting the results that are expected by project stakeholders.
Leadership is the ability to motivate and inspire individuals to work towards those expected results.
Management is the process of getting the results that are expected by project stakeholders.
Leadership is the ability to motivate and inspire individuals to work towards those expected results.
25.
Project
1.
Projects don't last
forever. They are temporary and unique
2.
Projects pass through
logical phases to reach their completion
3.
Purpose of Project is
to attain its objective and then terminate
26.
Operations
1.
Operations, however,
do go on and on. They are ongoing and repetitive
2.
Operations may be
influenced, or even created, by the outcome of a project
3.
Objective of an
ongoing operation is to sustain business
27.
Organization Structure
1.
Functional
2.
Matrix
1.
Weak
2.
Balanced
3.
Strong
3.
Projectized
28.
Organization Structure And Project Characteristics
1.
Functional
1.
PM's Authority [Little
or none]
2.
Resource Availability
[Little or none]
3.
Who controls Project
Budget [Functional Manager]
4.
PM's Role [Part -
Time]
5.
PM Admin Staff [Part -
Time]
2.
Weak Matrix
1.
PM's Authority
[Limited]
2.
Resource Availability
[Limited]
3.
Who controls Project
Budget [Functional Manager]
4.
PM's Role [Part -
Time]
5.
PM Admin Staff [Part -
Time]
3.
Balanced Matrix
1.
PM's Authority [Low to
moderate]
2.
Resource Availability
[Low to moderate]
3.
Who controls Project
Budget [Mixed]
4.
PM's Role [Full -
Time]
5.
PM Admin Staff [Part -
Time]
4.
Strong Matrix
1.
PM's Authority
[Moderate to high]
2.
Resource Availability
[Moderate to high]
3.
Who controls Project
Budget [Project Manager]
4.
PM's Role [Full -
Time]
5.
PM Admin Staff [Full -
Time]
5.
Projectized
1.
PM's Authority [High
to almost total]
2.
Resource Availability
[High to almost total]
3.
Who controls Project
Budget [Project Manager]
4.
PM's Role [Full -
Time]
5.
PM Admin Staff [Full -
Time]
29.
The WBS is a decomposition of all the deliverables the project
will create.
30.
WBS dictionary may
include, but is not limited to, code of account identifier, description of
work, assumptions and constraints, responsible organization, schedule
milestones, associated schedule activities, resources required, cost estimates,
quality requirements, acceptance criteria, technical references, and agreement
information. Reference: PMBOK® Guide - Fifth Edition, page 132
31.
Inspections may also be known as:
a. Reviews
b. Product reviews
c. Audits
d. Walk-throughs
a. Reviews
b. Product reviews
c. Audits
d. Walk-throughs
32.
Graphical evaluation
and review technique (GERT) models allow for loops and conditional
branching.
33.
Crashing adds more resources to activities to
decrease their duration, which typically adds cost.
34.
A Resource
histogram is just a way to visualize the number of
people in each role that you will
need on your project as time goes on. Once you have figured out your schedule
and the order of activities, you figure out how many people it's going to take to
do the work and plot that out over time. Then you have a good idea of what the
staffing needs of your project will be.
35.
The Staffing Management Plan always
includes a Resource Histogram, so that should be your first clue about
which one of these answers is right. The Resource Histogram shows what kind of
resource is needed through each week of your project and how many staff members
you need. When planning out your staffing needs, you need take into account the
training it will take to get them up to speed as well as the kinds of
incentives you are going to offer for a job well done. Release criteria are
important too, but they might not be familiar to you if you don't work in a
consulting organization. You need to think about what each staff member needs to
get done before they are released to work on other projects.
36.
Project calendar: This calendar shows when work is allowed
on the project. For example, a project may require the project team to work
nights and weekends so as not to disturb
the ongoing operations of the organization during working hours. In
addition, the project calendar accounts for holidays, working hours, and work
shifts that the project will cover
37.
Decision Trees are considered Quantitative while Influence diagram are considered Qualitative.
38.
Influence diagram shows the dependencies among the
variables more clearly than the decision tree
39.
Resource calendar: The resource calendar controls when resources,
such as project team members, consultants, and SMEs are available to work on
the project. It takes into account vacations, other commitments within the
organization, or restrictions on contracted work, overtime issues, and so on
40.
Program Evaluation and
Review Technique (PERT) uses a weighted average formula to predict
the length of activities and the project. Specifically, PERT uses a
'pessimistic,' 'optimistic,' and 'most likely' estimate to predict when the
project will be completed
41.
The critical path is the longest path to completion in the network diagram.
42.
Activities on the critical path have no
float or slack.
43.
Free float is the amount of time an activity can be
delayed without affecting the next activity's scheduled start date.
44.
Total float is the amount of time an activity can be
delayed without affecting the project end date.
45.
Total Float = LS – ES
or LF - EF
46.
Heuristic is simply a rule of thumb
47.
Crashing involves adding resources, which
typically increases cost.
48.
Fast tracking adds risk as tasks are allowed to
overlap
1.
Each resource in the project must be accounted for and
assigned to a cost category.
Categories include the following:
a. Labor costs
b. Material costs
c. Travel costs
d. Supplies
e. Hardware costs
f. Software costs
g. Special categories (inflation, cost reserve, and so on)
Categories include the following:
a. Labor costs
b. Material costs
c. Travel costs
d. Supplies
e. Hardware costs
f. Software costs
g. Special categories (inflation, cost reserve, and so on)
49.
There are three
generally accepted categories of estimating accuracy:
a. Rough order of magnitude This estimate is “rough” and is used during the Initiating processes and in top-down estimates. The range of variance for the estimate can be –25 percent to +75 percent or ( -50 to +50)
b. Budget estimate This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be –10 percent to +25 percent.
c. Definitive estimates This estimate type is one of the most accurate. It is used late in the planning processes and is associated with bottom-up estimating. The range of variance for the estimate can be –5 percent to +10 percent.
a. Rough order of magnitude This estimate is “rough” and is used during the Initiating processes and in top-down estimates. The range of variance for the estimate can be –25 percent to +75 percent or ( -50 to +50)
b. Budget estimate This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be –10 percent to +25 percent.
c. Definitive estimates This estimate type is one of the most accurate. It is used late in the planning processes and is associated with bottom-up estimating. The range of variance for the estimate can be –5 percent to +10 percent.
50.
The opportunity cost is the amount of the project that was not chosen
51.
Quality is the sum of the characteristics of a
product that allow it to meet the demands
or expectations of the project
or expectations of the project
52.
Grade, according to the PMBOK, “is a category or
rank given to entities having the
same functional use but different technical characteristics.”
For example, there are different grades of paint, different grades of metal, and even
different grades of travel.
same functional use but different technical characteristics.”
For example, there are different grades of paint, different grades of metal, and even
different grades of travel.
53.
The design of experiments (DOE) approach relies on statistical what-if
scenarios to determine what variables within a project will result in the best
outcome.
54.
Design of experiments is an analytical technique that identifies the
elements or
variables that will have the greatest effect on overall project outcomes
variables that will have the greatest effect on overall project outcomes
55.
There are five types
of powers the project manager yields: (R F C E R)
a. Reward
b. Formal
c. Coercive (penalty)
a. Reward
b. Formal
c. Coercive (penalty)
d. Expert
e. Referent
e. Referent
56.
Among the above
powers Reward, Formal & Coercive (penalty) come with the "Position"
57.
Expert & Reward are considered the best types of powers and Coercive (penalty) is "Least" for obvious reasons
58.
Seven reasons for
conflict, in order of most common to least common:
a. Schedules
b. Priorities
c. Resources
d. Technical beliefs
e. Administrative policies and procedures
f. Costs
g. Personalities
a. Schedules
b. Priorities
c. Resources
d. Technical beliefs
e. Administrative policies and procedures
f. Costs
g. Personalities
59.
Five different
approaches to conflict resolution
a. Confronting (Problem Solving) (win - win) [BEST]
b. Forcing (win - lose)
c. Compromising (lose - lose)
d. Smoothing
e. Withdrawal
NOTE: Forcing (win - lose) and Problem Solving (win - win) are the ONLY two modes that result in a RESOLUTION to the conflict.
a. Confronting (Problem Solving) (win - win) [BEST]
b. Forcing (win - lose)
c. Compromising (lose - lose)
d. Smoothing
e. Withdrawal
NOTE: Forcing (win - lose) and Problem Solving (win - win) are the ONLY two modes that result in a RESOLUTION to the conflict.
60.
The halo effect is the promoting the person to manage projects since
he/she is good at a technology
61.
Within communicating there are five characteristics that affect the message:
a. Paralingual: pitch, tone, and voice inflections
b. Feedback: sender confirmation of the message by asking questions, for a
response, or other confirmation signals
c. Active listening: receiver confirms message receipt
d. Effective listening: receiver offers confirmation of the message, such as nodding
their head, asking questions, or other interactions.
e. Nonverbal: facial expressions, hand gestures, and body language
a. Paralingual: pitch, tone, and voice inflections
b. Feedback: sender confirmation of the message by asking questions, for a
response, or other confirmation signals
c. Active listening: receiver confirms message receipt
d. Effective listening: receiver offers confirmation of the message, such as nodding
their head, asking questions, or other interactions.
e. Nonverbal: facial expressions, hand gestures, and body language
62.
One of the first
inputs to risk management is the project charter.
63.
Historical
information is always an excellent
source of information for risk identification
64.
Brainstorming is likely the most common approach to risk
identification
65.
Force majeure is a powerful and unexpected event, such
as a hurricane or other disaster
66.
Contracts are known by many names:
a. Agreement
b. Subcontract
c. Purchase order
d. Memorandum of understanding
a. Agreement
b. Subcontract
c. Purchase order
d. Memorandum of understanding
67.
All contracts in
the United States are backed by the US court systems.
68.
Liquidated damages (LDs) are
contractually agreed payments in order to cover
the customer's costs caused by late completion or failure to meet
specifications by the contractor.
69.
Constructive change -A
direction by the buyer or an action taken by the seller that the other party
considers an undocumented change to the contract.
70.
According to the Guide
to the PMBOK, the project charter should be published by a manager external to the
project but with sufficient power and authority to carry it off.
71.
Journey to Abilene -Committee
decisions can have the paradox outcome, that a jointly made or approved
decision is not desired by any individual group member.
72.
When a project is
performed under contract, the contract can serve as the project charter
73.
Cost reimbursable
contracts are used when the degree
of uncertainty is high and when the project requires a large investment prior
to completion of the project
74.
When there's a dispute
between a buyer and a seller, that's called a claim.
75.
The scope statement contains an exhaustive list of the project deliverables,
their requirements, and measurable criteria used to determine project
completion
76.
The scope statement is an output to the Scope Definition process and is used to
create the WBS
77.
Cause-and-effect
diagrams, also called Ishikawa
or fishbone diagrams, show the relationship between the effects of quality
problems and their causes
78.
The primary function of
the Closing process is to formalize project completion and disseminate
this information to the project participants
79.
According to the Guide
to the PMBOK, the project manager is identified and assigned as an output of
the Initiation process. In practice, project managers are very often assigned
at the beginning of this process.
80.
The work package level is the lowest level in the WBS. Time and
cost estimation is easily determined at this level as are resource assignments.
Quality control measurements can be determined at this level as well.
81.
The code of accounts is assigned to the elements in the WBS Each element in the
WBS is assigned a unique identifier. These are collectively known as the code of accounts
82.
The Responsibility
Assignment Matrix (RAM) links
project roles and responsibilities with project activities
83.
The WBS is the deliverables-oriented hierarchy of project work.
84.
The staffing management plan details how and when human resources will
be added to and taken off the project. It is an output of Organizational
Planning
85.
Analogous estimating is not a qualitatively based technique. It
is a top-down estimating technique that considers previous similar activities
when calculating estimates
86.
Mandatory dependency, also known as hard logic. Mandatory
dependencies are inherent in the nature of the work
87.
Discretionary
dependencies, also called preferred
logic, preferential logic, and soft logic, are defined by the project
management team
88.
"Best Practice”
often refers to a specific sequence of work, described in terms of “Soft Logic”. Sometimes "Experience" is also attributes to Soft
Logic
89.
Finish to start is the
most commonly used logical relationship in PDM and most project management
software packages
90.
Finish-to-Start
PMBOK® Definition: The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity.
Layman’s Definition: Once this task finishes, we can start the next one.
PMBOK® Definition: The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity.
Layman’s Definition: Once this task finishes, we can start the next one.
91.
Start-to-Start
PMBOK® Definition: The logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity. See also logical relationship.
Layman’s Definition: We want these two tasks to start at the same time.
PMBOK® Definition: The logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity. See also logical relationship.
Layman’s Definition: We want these two tasks to start at the same time.
92.
Finish-to-Finish
PMBOK® Definition: The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity. See also logical relationship.
Layman’s Definition: We want these two tasks to finish at the same time.
PMBOK® Definition: The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity. See also logical relationship.
Layman’s Definition: We want these two tasks to finish at the same time.
93.
Start-to-Finish
PMBOK® Definition: The logical relationship where the completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity. See also logical relationship.
Layman’s Definition: This task finishes when the next one starts, but not before then.
PMBOK® Definition: The logical relationship where the completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity. See also logical relationship.
Layman’s Definition: This task finishes when the next one starts, but not before then.
94.
There are three major documents and each has a specific purpose:
a. Project Charter. Formally authorizes the project.
b. Project Scope Statement. States what work is to be accomplished and what
deliverables need to be produced.
c. Project Management Plan. States how the work will be performed
a. Project Charter. Formally authorizes the project.
b. Project Scope Statement. States what work is to be accomplished and what
deliverables need to be produced.
c. Project Management Plan. States how the work will be performed
95.
Philip Crosby devised the zero defects theory, meaning do it right the first time. Proper Quality Planning
leads to less rework and higher productivity
96.
According to Bruce Tuckmann, “Forming, Storming, Norming and Performing ” are the stages of
team development
97.
The performing stage
is similar to Maslow’s self-actualization
98.
Myers Brigg’s theory states that “Sensing” and “Intuition”
personality types are related to “Information” preference in other words ‘Hard
Data verses what might be’
99.
Juran = Fitness for use, conformance. Quality
by design.
100.
Joseph M. Juran is noted for his fitness for use
premise. Simply put, this means the stakeholders’ and customers’ expectations
are met or exceeded.
101.
W. Edwards Deming suggested that as much as 85 percent of
the cost of quality is a management problem
102.
Shewhart = Plan-Do-Check-Act cycle.
103.
TQM = Quality must be managed in and must be
a continuous process
104.
Six Sigma = Six Sigma is a measurement-based strategy;
no more than 3.4 defects per million.
105.
Kaizen = Continuous improvement; improve
quality of people first.
106.
Continuous improvement
= Watch continuously for ways to improve quality.
107.
Peter Principle: Project
team members are motivated in an opportunity to grow.
108.
Statement of work (SOW) comprises
of
1.
Business Need, Product Scope Description and Strategic
Plan
109.
Conflict should be addressed early and usually in
private, using a direct, collaborative approach
110.
Organization,
Environmental & external assumptions should be addressed by the Project Charter
111.
WBS Dictionary” is a document which describes the details for
each component in the WBS. It includes a brief description of the of the
“Scope” or “Statement of the work” , defined deliverables, a list of associated
activities, and a list of milestones
112.
Project Manager must
consider “cultural differences” while deciding upon recognition and rewards
during team development.
113.
Technical inability and
poor risk management by the contractor is mostly the reason for the
project not to meet the
customer expectations
114.
Critical Chain Project Management” is
typically the “Management of Buffers”
115.
Critical Chain is another schedule network analysis
technique that modifies the project schedule to account for limited resources
116.
The Critical Chain method adds duration buffers that are non-work schedule
activities to maintain focus on the planned activity durations
117.
Cost Of Quality (COQ) are the cost types in modern quality management
1.
“Prevention Costs”,
2.
“appraisal costs”
&
3.
“failure costs” (
Internal and External)
118.
The key components of the communication model include:
a. Encode.
b. Message.
c. Medium.
d. Noise.
e. Decode.
a. Encode.
b. Message.
c. Medium.
d. Noise.
e. Decode.
119.
Common formats
for performance reports include
1.
Bar charts,
2.
S curves,
3.
Histograms, and
4.
Tables.
120.
Face-to-face meetings
are the most effective means
for communicating and resolving
issues with stakeholders.
issues with stakeholders.
121.
Order of Magnitude estimates are also knows as conceptual, ballpark or
preliminary
estimates
estimates
122.
“Tight Matrix” is putting all project personnel together.
Also referred as “collocated”
123.
Strategies for “Negative Risks or threats” (Avoid Transfer Mitigate)
124.
Strategies for “Postive Risks or Opportunities” (Share Exploit Enhance Accept)
125.
Common Strategy for both threats and
opportunities is “Acceptance”
126.
There are 3 stages of “reaction to stress” (Alarm, Resistance & Exhaustion)
127.
Some of the traits/qualities exhibited by effective leaders are
1.
Flexibility,
2.
Ambition,
3.
Intelligence,
4.
Decisiveness,
5.
Creativity,
6.
Persistence and
7.
Energy
128.
Detailed Tasks are
detailed in “Project Schedule”, which is part of Project Plan and note its
NOT WBS. WBS is a “deliverable oriented document”
129.
An abnormal trend is formed when seven or more consecutive data points
reflect a steadily increasing or decreasing pattern over time
130.
Scope
Verification is concerned with the
acceptance of deliverables
131.
Quality control is concerned with making sure the
deliverables meet quality
requirements. Quality Control is done first; both are Monitoring and Controlling
processes.
requirements. Quality Control is done first; both are Monitoring and Controlling
processes.
132.
Quality Assurance
(Executing) is focused on
process: process analysis, quality audits, etc.
·
Quality Audits helps
to improve process implementation and team productivity.
·
Quality audits help to
share best practices in one project with other projects in the organization.
·
Quality Audits are
used to identify all the best practices implemented in the project.
133.
Quality Control
(Monitoring and Controlling) is focused on sampling results to see if they meet quality
standards
134.
Merrill and Reid in
their employee motivation theory define the following personal styles, viz. Driver, Amiable, Expressive, and Analytical.
135.
Code of Accounts identifies WBS items; Chart of Accounts monitors project costs by category
136.
In decision tree, a circle is a chance. (A circle
represents a "chance node," meaning a chance to which an Expected
Monetary Value (EMV) may be assigned to calculate the most likely pay-off.)
137.
In Precedence Diagramming Method (PDM) or Activity on Node (AON) network diagrams, nodes are activities and
arrows are dependencies
138.
In Arrow Diagramming Method (ADM) or Activity on Arrow (AOA) network diagrams, arrows are activities and
nodes are dependencies
139.
Dummies are only used
on ADM
140.
ADM tasks can only have FS relationships
141.
PDM uses one time estimate to determine
duration, while ADM can use more than one time estimate.
142.
Scope Verification is done during Project monitoring and controlling BUT Product verification is done during the Project
Closing
143.
Privity – legal
contractual relationship
144.
Audits:
o Quality Audit in Perform QA,
o Risk Audit in Risk Monitoring and Control,
o Inspections and Audits in Contract Administration,
o Procurement Audits in Close Contracts
o Quality Audit in Perform QA,
o Risk Audit in Risk Monitoring and Control,
o Inspections and Audits in Contract Administration,
o Procurement Audits in Close Contracts
145.
The outputs of process groups are:
o initiating: charter and preliminary scope statement;
o planning: project management plan;
o executing: work results;
o monitoring: corrective actions;
o closing: project product.
o initiating: charter and preliminary scope statement;
o planning: project management plan;
o executing: work results;
o monitoring: corrective actions;
o closing: project product.
146.
Reporting formats:
o Forecast Report (what is expected to happen on a project),
o Progress Report (what happened since the last report),
o Status Report (state of the project at the current time),
o Earned Value Report (focuses on Earned Value Management),
o Variance Report (what happened vs. what should have happened).
o Forecast Report (what is expected to happen on a project),
o Progress Report (what happened since the last report),
o Status Report (state of the project at the current time),
o Earned Value Report (focuses on Earned Value Management),
o Variance Report (what happened vs. what should have happened).
147.
Performance Reporting is a Controlling process. It creates
Performance Reports, which are comparisons of performance to the performance
baselines. These are typically done in tabular or graphical format.
148.
Information
Distribution is an Executing
process. It creates Organizational Process Assets such as project
presentations, stakeholder notifications and status reports.
149.
Develop Project Team is an Executing Process. It creates a
Team Performance Assessment, and helps you determine what additional training
would be beneficial.
150.
Manage Project Team is a Controlling Process. It creates
input to performance appraisals as well as recommended changes, corrective
actions and preventative actions.
151.
Scope Baseline includes
1.
Project Scope Statement, WBS, & WBS Dictionary
152.
A large portion of the
PM’s time while the work is being done is spent measuring and implementing
corrective actions
153.
Project Close Process includes creation of two procedures
o Administrative closure procedure and
o Contract closure procedure
o Administrative closure procedure and
o Contract closure procedure
The difference between the two is focus,
formality and frequency.
Administrative closure focuses on closing the
project or project phase whereas
Contract closure focuses on closing a contract
that is part of the project
154.
Contingency
Reserve (Known Unknowns) is
for the risks remaining after the Risk Response Planning
Management Reserve (Unknown Unknowns) is any extra amount reserved t cover “unforeseen risks”
Cost Baseline will include the Contingency Reserve
Cost Budget will include the Management Reserve
Management Reserve (Unknown Unknowns) is any extra amount reserved t cover “unforeseen risks”
Cost Baseline will include the Contingency Reserve
Cost Budget will include the Management Reserve
155.
The values that the global project management
community defined as most important were: Responsibility,
Respect, Fairness, and Honesty.
156.
Quality is defined as the degree to which the
project fulfills requirement
157.
Quality MUST BE PLANNED IN AND NOT INSPECTED IN
158.
The Project Manager ultimately has the responsibility for the Product of the
Project
159.
Senior Management is responsible for the Quality of entire
Organization
160.
Cost of Nonconformance
is greater than the cost of conformance
161.
Most projects will fit
one of the six needs and demands
·
Market demand
·
Business need
·
Customer request
·
Technological advance
·
Legal requirement
·
Social need
162.
The project charter (which is an output of the Develop the Project Charter
process) is the ritten acknowledgment that the project exists. The project
charter names the project
manager and gives that person the authority to assign organizational resources to the
project
manager and gives that person the authority to assign organizational resources to the
project
163.
Net present value (NPV) assumes reinvestment is made at the cost
of capital. If you're asked to choose between projects and
given the NPV of each of them, choose the one with the biggest NPV. That means
you're choosing the one with the most value!
164.
If the NPV is greater than or equal to zero dollars, accept the
project.
165.
IRR assumes reinvestment at the IRR rate and is
the discount rate when NPV is equal to zero. Discounted cash flow = IRR
166.
Payback period does not consider the time value of
money and is therefore the least precise
of all the cash flow analysis techniques
167.
Preliminary project
scope statement describes the objectives of the project and the high level
requirements needed to satisfy stakeholder expectations
168.
The PMIS in the Develop
Project Management Plan process includes a subsystem called the configuration
management system ( PMIS includes CMS)
169.
Change control system, which is a subsystem of the configuration
management system
170.
Stakeholder analysis is a tool and technique of Identify Stakeholder used to determine
and document the needs, wants, and expectations of stakeholders and prioritize
and quantify those needs into project requirements
171.
You, as the project
manager, are planning to document relevant information on interests,
involvement, influence, and impact of project stakeholders. Which of the
following processes should you follow?
Choice 1 Stakeholder
Analysis
Choice 2 Plan
Communications Management
Choice 3 Manage
Stakeholder Engagement
Choice 4 Identify
Stakeholders
Justification :
Option 1: Stakeholder
Analysis is a technique used to identify and classify stakeholders and their
interests. It is used when identifying stakeholders; however, it is not the
name of the process itself.
Option 2: Plan
Communications Management is the process of determining the information needs
of the project stakeholders and defining a communication approach to satisfy
those needs.
Option 3: Manage
Stakeholder Engagement is an executing process which involves working with
stakeholders to meet their expectations. The current project is in the
initiating phase as stakeholder-related details are just being gathered.
Option 4: Identify
Stakeholders is the process used to identify all those people or organizations
impacted by the project and document relevant information on their interests,
involvement, and impact on the success of the project. Hence Correct Choice: 4
172.
The purpose of
the project scope
statement is to document
the project objectives, deliverables, and requirements so that they can be used
to direct the project team’s work and as a basis for future project decisions
173.
The scope statement further elaborates the project objectives, deliverables,
requirements, and constraints and assumptions defined in the preliminary scope
statement. It serves as a basis for future project decisions
174.
Alternatives analysis or Alternative Generation
is a tool and technique of the Define Scope process that includes brainstorming
and lateral thinking techniques
175.
Poor scope definition
might lead to cost increases, rework, schedule delays, and poor morale
176.
According to the PMBOK
Guide, functionality and specific conditions that must be met in order to
satisfy the project, contract, standard, or specification describe the criteria
for requirements, not objectives
177.
Product analysis (TT Scope Definition) includes
techniques such as value engineering, value analysis, systems analysis, systems
engineering, product breakdown, and functional analysis.
178.
Product analysis includes techniques such as
product breakdown, systems analysis, requirements analysis, systems
engineering, value engineering, and value analysis.
179.
The product scope description can be used as an input to the Scope
Definition process when the project charter and/or preliminary project scope
statement are missing
180.
The lowest level of
any WBS is called the work package level
181.
For the exam, remember
that the key to DOE is that it equips you with a statistical framework that
allows you to change the variables that have the greatest effect on overall project
outcomes at once instead of changing one variable at a time.
182.
Quality checklists are
an output of the Quality Planning process, and checklist analysis is a tool and
technique of the Risk Identification process
183.
Cost-benefit analysis
considers trade-offs in the Quality Planning process
184.
Benchmarking compares
previous similar activities to the current project activities to provide a
standard to measure performance against. Benchmarking is the
process of comparing one's business processes and performance metrics to
industry bests or best practices from other industries.
Dimensions typically measured are quality, time and cost. In the process of
best practice benchmarking, management identifies the best firms in their
industry, or in another industry where similar processes exist, and compares
the results and processes of those studied (the "targets") to one's
own results and processes. In this way, they learn how well the targets perform
and, more importantly, the business processes that explain why these firms are
successful.
185.
Failure costs; is also known as the cost of poor quality. Failure costs include both
internal and external costs.
Internal failure costs are costs associated with not meeting the customer’s expectations while you still had control over the product. This results in rework, scrapping, and downtime.
Internal failure costs are costs associated with not meeting the customer’s expectations while you still had control over the product. This results in rework, scrapping, and downtime.
186.
Marginal cost is
another term for variable cost. The marginal cost is applied to the variable
cost of a unit of product or service.
187.
Once the risks have
been identified on the project, the next step is to manage the risks. Of the
following, which is NOT a suitable way of managing the risks?
·
By using existing
assets
·
By contingency
planning
·
By investing in new
resources
·
By Brainstorming
Answer: Brainstorming.
Brainstorming is a tool and technique for risk identification. All of the other
options are ways of managing the risks. Existing assets may involve
improvements to existing methods and systems, changes in responsibility, etc.
Contingency planning may help you in minimizing the effect, if it happens.
Investing in new resources may help in reducing or insuring you against risk.
188.
The process improvement plan is a subsidiary plan of the project
management plan and targets inefficiencies in a process or activity. The
quality baseline is used to document the uality objectives of the project and
is used as a basis for future Quality processes.
189.
An issue log is the output of Manage stakeholder
engagements
190.
The WBS dictionary should be documented with the code of account identifier, an SOW, the
responsible organization, and a milestone schedule for the WBS components
191.
Design of experiments is a tool and technique of the Quality
Planning process that provides
statistical analysis for changing key product or process elements all at once (not one at a
time) to optimize the process
192.
According to the PMBOK
Guide, the risk management plan should include the following
elements:
o Methodology
o Roles and responsibilities
o Budgeting
o Timing
o Risk categories
o Definitions of risk probability and impact
o Probability and impact matrix
o Revised stakeholder tolerances
o Reporting formats
o Tracking
elements:
o Methodology
o Roles and responsibilities
o Budgeting
o Timing
o Risk categories
o Definitions of risk probability and impact
o Probability and impact matrix
o Revised stakeholder tolerances
o Reporting formats
o Tracking
193.
The output of
the Risk Identification
process is the risk register.
The risk register contains
the following elements:
o List of identified risks
o List of potential responses
o Root causes of risks
o Updated risk categories
the following elements:
o List of identified risks
o List of potential responses
o Root causes of risks
o Updated risk categories
194.
Risk urgency
assessment is a tool and technique of Qualitative Risk Analysis process
195.
Qualitative Risk
Analysis is a fast and
easy method of determining probability and impact
196.
The risk management
plan details how risk management processes will be implemented,
monitored, and controlled throughout the life of the project.
monitored, and controlled throughout the life of the project.
197.
The risk management plan
does not include responses to risks or triggers. Responses to
risks are documented in the risk register as part of the Risk Response Planning process
risks are documented in the risk register as part of the Risk Response Planning process
198.
The information-gathering techniques in the Risk Identification process are
o brainstorming,
o the Delphi technique,
o interviewing,
o root cause identification, and
o SWOT analysis.
o brainstorming,
o the Delphi technique,
o interviewing,
o root cause identification, and
o SWOT analysis.
199.
Quantitative Risk
Analysis analyzes the probability of risks and their consequences using a numerical
rating
200.
Monte Carlo analysis is a simulation technique
& not a Modeling technique
201.
When the question
describes sensitivity analysis, which is a tool and technique of the Quantitative
Risk Analysis process. Tornado diagrams are often used to display sensitivity analysis
data
202.
The simplest form of
“Risk Analysis” is “Sensitivity Analysis”
203.
Following options are
diagramming techniques of the Risk Identification process
o Ishikawa diagram
o Process flowchart
o Influence diagram
o Ishikawa diagram
o Process flowchart
o Influence diagram
204.
Passive acceptance is when the team has decided to take no
action and make no plans for
the risk. This is a strategy that can be used for either positive or negative risks.
the risk. This is a strategy that can be used for either positive or negative risks.
205.
The PMBOK Guide
divides contracts
into three categories:
o Fixed price or lump sum (biggest risk is borne by the seller & good when original scope is well defined)
o Cost reimbursable (biggest risk is borne by the buyer)
o Time and materials (T&M)
o Fixed price or lump sum (biggest risk is borne by the seller & good when original scope is well defined)
o Cost reimbursable (biggest risk is borne by the buyer)
o Time and materials (T&M)
206.
The three outputs of
the Plan Contracting process are
1) Procurement documents (Request for proposal (RFP), Request for information (RFI), Invitation for bid (IFB), Request for quotation (RFQ)),
1) Procurement documents (Request for proposal (RFP), Request for information (RFI), Invitation for bid (IFB), Request for quotation (RFQ)),
2) Evaluation
criteria, and
3) Contract statement of work updates.
207.
Understand the
difference between bid and/or quotation and proposal for the exam. Bids or
quotations are used when price is the only deciding factor among bidders.
Proposals are used when there are considerations other than price
208.
Status reports via
email to all the stakeholders – example of Push Communications
209.
A contract statement of work (SOW) contains the details of the procurement
item in clear, concise terms. It includes the following elements:
o The project objectives
o A description of the work of the project and any post project operational support needed
o Concise specifications of the product or services required
o The project schedule, time period of services, and work location
o The project objectives
o A description of the work of the project and any post project operational support needed
o Concise specifications of the product or services required
o The project schedule, time period of services, and work location
210.
According to the PMBOK
Guide, using templates and checklists is one way to ensure that you don’t miss
any key responsibilities when planning the project and will help reduce the amount
of time spent on project planning
211.
According to the PMBOK
Guide, the RAM (Responsibility Assignment Matrix)
relates the OBS to the WBS to assure that every component of the work of the
project is assigned to an individual.
212.
The letters in the
acronym RACI (sample portion of a type of RAM) are
the designations are
o R = Responsible for performing the work
o A = Accountable, the one who is responsible for producing the deliverable or
work package and approves or signs off on the work
o C = Consult, someone who has input to the work or decisions
o I = Inform, someone who must be informed of the decisions or results
o R = Responsible for performing the work
o A = Accountable, the one who is responsible for producing the deliverable or
work package and approves or signs off on the work
o C = Consult, someone who has input to the work or decisions
o I = Inform, someone who must be informed of the decisions or results
213.
A project manager in
an MNC corporation is in the process of collecting, organizing, and
disseminating information on how project resources are being used to complete
project objectives. In addition, he is collating information on cost, schedule,
and level of quality. He is also going through the influence of risks on
project objectives. The project manager is in which process?
·
Direct and Manage
Project Work
·
Manage Communications
·
Earned Value Technique
·
Monitor and Control
Project work
Explanations:
214.
Answer (b) Manage
communications. The project manager
is in 'Manage Communications' process as part of communication management. It
is the process of collecting and distributing performance information,
including status reports, progress measurements and forecasts. For more
information on the process please refer to PMBOK 5th edition Project
Communications Management PN 303.
215.
It is during the initiating process group that we
identify and document high level risks, assumptions and constraints in order to
identify project limitations and thereafter propose an implementation approach.
216.
You are a project
manager taking over a project midway. It is in the execution phase. You would
like to know more about project deliverables, work required to complete those
deliverables, project constraints, assumptions, etc. Which of the following
documents would be MOST useful?
·
Work Breakdown
Structure (WBS) and WBS dictionary
·
Requirements
Documentation
·
Activity List
·
Project Scope
Statement
Explanations:
217.
Answer (d) Project Scope Statement. The project manager should refer to the
project scope statement as it captures
all of the details related to the project scope including product acceptance
criteria, scope description, project deliverables, constraints, assumptions, etc. Option (a) and option (c) define project
scope at the smaller work package and activity level respectively. Option (b)
Requirements Documentation captures requirements of the project related to
quality, functional and non-functional requirements, support requirements, etc
and is an incorrect.
218.
Configuration
Management System:
·
The purpose of
configuration management is to maintain
integrity of work product
·
Configuration
management includes configuration audits,
configuration control ,configuration status accounting and configuration
identification
·
Configuration
management focuses on establishing and maintaining consistency
of a product's requirements
219.
The RAM and RACI
charts are tools and techniques of Human Resource Planning process
220.
Standard forms are a tool and technique of the Plan
Contracting process. Standard forms
can be nondisclosure agreements, standardized contracts, and so on.
can be nondisclosure agreements, standardized contracts, and so on.
221.
Plan Purchases and
Acquisitions can directly influence the project schedule, and the project
schedule can directly influence this process
222.
Resource availability is an output of the Acquire Project Team
and Select Seller processes
223.
For the exam, remember
that resource availability isn’t determined until the Executing stage and
becomes an input to the Activity Resource Estimating process
224.
The higher the
standard deviation is for an activity, the higher the risk. Since standard deviation
measures the difference between the pessimistic and the optimistic times, a greater
spread between the two, which results in a higher number, indicates a greater
risk. Conversely, a low standard deviation means less risk
225.
Monte Carlo is a simulation technique that shows the probability of all the possible project completion dates
226.
Resource leveling can
cause the original critical path to change.
227.
When you're performing the Close Procurements process, you're closing out work done
by a seller for a contract. To do that, you do a few things: you verify that
all of the work and deliverables are acceptable, you finalize any open claims,
and in case of early termination, you follow the termination clause in the
contract. On the other hand, when you're performing the Close Project or Phase process,
you're finalizing all of the various activities that you do across all of the
process groups, and you're also verifying that the work and deliverables are
complete. Procurement closure means verifying that the
project is complete or terminated; Close Project or Phase is the process of
tying up all of the activities for every management process group.
228.
Requirements documentation and the project scope
statement are the sources
of information about specific project constraints and assumptions
229.
CPM manages the total
float of schedule networks paths, whereas critical chain manages buffer
activity durations and resources
230.
Cost aggregation (TT of Cost Budgeting) is the process of
tallying the schedule activity cost estimates at the work package level and
then totaling the work package levels to higher level WBS component levels
231.
Funding limit
reconciliation (TT of Cost
Budgeting) involves reconciling the amount of funds spent with the amount of
funds budgeted for the project
232.
Cost baselines are
displayed as an S curve.
233.
The primary output of Estimate
Cost is Activity Cost Estimates.
234.
Parametric
estimating multiplies a known
element—such as the quantity of materials needed—by the time it takes to
install or complete one unit of materials. The result is a total estimate for
the activity
235.
The project schedule
determines the start and ending dates of activities, determines float times,
generally shows resource assignments, and details the activity sequences and durations.
236.
Motivation can be
extrinsic or intrinsic.
o Extrinsic motivators are material rewards and might include bonuses, the use of a company car, stock options, gift certificates, training opportunities, extra time off, and so on
o Intrinsic motivators are specific to the individual. Some people are just naturally driven to achieve—it’s part of their nature.
o Extrinsic motivators are material rewards and might include bonuses, the use of a company car, stock options, gift certificates, training opportunities, extra time off, and so on
o Intrinsic motivators are specific to the individual. Some people are just naturally driven to achieve—it’s part of their nature.
237.
The introduction of
a new team member will start the formation and development of
the team all over again with the forming stage
238.
Teams in the norming
stage of Develop Project Team exhibit affection and familiarity with one
another and make joint decisions
239.
Request Seller
Responses obtains bids and
proposals from vendors.
240.
Select Sellers is the receipt of bids and proposals and
the selection of a vendor
241.
Independent estimates
(TT of Select Sellers), also called should cost estimates, are a way to check
proposed pricing
242.
Fait accompli is a tactic used during contract negotiations where one party convinces the other that the
particular issue is no longer relevant or cannot be changed
243.
The process analysis technique (TT of Perform Quality Assurance process)
includes root cause analysis to analyze a problem and solution and to create
preventive actions
244.
You are preparing
project performance appraisals and have decided you’d like each team member to
get feedback regarding their performance from several sources, including peers,
superiors, and subordinates. This is called 360-degree feedback and is part of
the project performance appraisals tool and technique of the Manage Project
Team process.
245.
Understand for the
exam that configuration
management involves
o identifying the physical characteristics of the product, service, or result of the project (or its individual components);
o controlling changes to those characteristics; and
o Documenting changes to verify that requirements are met.
o It also includes the change management system and
o documents the process for requesting, tracking, and determining whether change requests should be approved or denied.
o identifying the physical characteristics of the product, service, or result of the project (or its individual components);
o controlling changes to those characteristics; and
o Documenting changes to verify that requirements are met.
o It also includes the change management system and
o documents the process for requesting, tracking, and determining whether change requests should be approved or denied.
246.
Activities associated
with configuration change
management in the
Integrated Change Control process
o Configuration identification
o Configuration status accounting and
o Configuration verification and auditing
o Configuration identification
o Configuration status accounting and
o Configuration verification and auditing
247.
Integrated Change
Control, Schedule
Control, and Cost Control are all concerned with three issues:
o influencing the things that cause change,
o determining that change is needed or has happened,
o and managing the change
o influencing the things that cause change,
o determining that change is needed or has happened,
o and managing the change
248.
Change control systems are documented procedures that describe
o How to submit change requests.
o They track the status of the change requests,
o document the management impacts of change,
o track the change approval status, and
o define the level of authority needed to approve changes.
o How to submit change requests.
o They track the status of the change requests,
o document the management impacts of change,
o track the change approval status, and
o define the level of authority needed to approve changes.
249.
Change control
systems do not approve or deny
the changes—that’s the responsibility of the configuration control board (CCB)
250.
The configuration
control board (CCB) has the authority to approve or deny change requests. Their
authority is defined and outlined by the organization
251.
“Recommended” corrective action is an output of several of the change
control processes, including Scope Change Control, Schedule Control, Cost
Control, Risk Monitoring and Control, and Perform Quality Control.
252.
“Approved” corrective action is an output of the
Integrated Change Control process.
Remember that Integrated Change Control is where all change requests are processed and either approved or denied.
Remember that Integrated Change Control is where all change requests are processed and either approved or denied.
253.
Also note that
corrective action is an output of the Monitoring and Controlling processes and
an input to the Executing processes
254.
Cost variances (both positive and negative) are
calculated using a performance
measurement analysis tool (specifically earned value techniques)
measurement analysis tool (specifically earned value techniques)
255.
EVT (earned value
techniques) compares what you’ve
received or produced to what you’ve spent.
256.
Workarounds are
unplanned responses. Workarounds deal with negative risk events as they occur.
257.
Schedule variances
will sometimes—but not always—impact the schedule. Changes to noncritical path
tasks will not likely impact the schedule, but changes to critical path tasks will
always impact the schedule
258.
Budget updates might require cost rebase lining
259.
The process improvement plan is more focused on enhancing the value of the process in a project. It includes determining process
boundaries, process metrics, targets for improved performances, etc.
260.
You can remember the
difference between Scope Verification and Perform Quality Control this way:
o Scope Verification = accepting work results
o Perform Quality Control = checking for correct work results (assuring that the
quality requirements are met)
o Scope Verification = accepting work results
o Perform Quality Control = checking for correct work results (assuring that the
quality requirements are met)
261.
Projects come to an
end for several reasons:
o They’re completed successfully.
o They’re canceled or killed prior to completion.
o They evolve into ongoing operations and no longer exist as projects.
o They’re completed successfully.
o They’re canceled or killed prior to completion.
o They evolve into ongoing operations and no longer exist as projects.
262.
Four formal types of project endings exist that you might need to know for
the exam:
o Addition
o Starvation
o Integration
o Extinction
o Addition
o Starvation
o Integration
o Extinction
263.
For the exam, remember
that product verification performed during the Closing processes determines
whether all of the work of the project was completed correctly according to the
contract terms and satisfactorily according to stakeholder expectations,
whereas product documentation is verified and accepted during the Scope
Verification process. One more note: when projects end prematurely, the Scope
Verification process is where the level of detail concerning the amount of work
completed gets documented.
264.
Note PMI defines “Scope Statement” as the basis for making future project decisions and for
confirming or developing common understanding of project scope among project
stakeholders.
stakeholders.
265.
Close Project
o Product verification (work was correct and satisfactory)
o Collecting project documents
o Disseminating final acceptance notice
o Documenting lessons learned
o Archiving project records
o Product verification (work was correct and satisfactory)
o Collecting project documents
o Disseminating final acceptance notice
o Documenting lessons learned
o Archiving project records
266.
Contract Closure
o Product verification (work was correct and satisfactory)
o Formal acceptance and closure
o Product verification (work was correct and satisfactory)
o Formal acceptance and closure
267.
WBS element changes
are scope changes. Schedule revisions are often required as a result of scope
changes.
268.
Close Project and
Contract Closure are the
processes in the Closing process group and are
performed in that order
performed in that order
269.
The work performance
information is reviewed to determine the status of project activities
and make certain the project goals and objectives are met. This is an input to the Close
Project process
and make certain the project goals and objectives are met. This is an input to the Close
Project process
270.
According to the PMBOK
Guide, the procurement audit examines the procurement process
from Procurement Planning through Contract Administration
from Procurement Planning through Contract Administration
271.
Integrity means
adhering to an ethical standard
272.
Hammocks are
summary-level activities or aggregate activities shown as a summary activity on
a project schedule network diagram.
273.
Contract Negotiation has “5’ Sequential steps (Note Agreement
is AFTER Closure)
o Protocol
o Probing
o Scratch Bargaining
o Closure and
o Agreement
o Protocol
o Probing
o Scratch Bargaining
o Closure and
o Agreement
274.
The Primary Objective
of establishing a Quality Assurance Process is “For Quality Improvement”
275.
“Quality Function
Deployment Process” identifies what the customer’s needs are
(Spoken/unspoken words) and translates those needs into technical requirements. Appropriate for each stage of the product development life cycle
(Spoken/unspoken words) and translates those needs into technical requirements. Appropriate for each stage of the product development life cycle
276.
Decision Tree is a
diagram that describes a decision under consideration and the implications of
choosing one of the alternatives
277.
The Project Charter provides the
o high level requirements,
o constraints,
o assumptions,
o stakeholders and
o the measures of success.
o high level requirements,
o constraints,
o assumptions,
o stakeholders and
o the measures of success.
278.
Based on this
information, or the lack of it, the Charter is an excellent source to start to identify
the Project Risks
279.
Activity Resource
Estimating involves
determining what physical resources (People, Equipment, etc) and what
quantities should be used and when they would be needed to perform project
activities
280.
Physical limitations
are an attribute of “Mandatory Dependencies”
281.
A Project Phase is
“Marked by the completion of one or more deliverables”
282.
A “Product Description” should define the relationship between the
product that is being created and the business need
283.
Contingency Plans can
be best described as “Planned responses to Risk Events”
284.
Staff assignments and
resource availability are the outputs of “Acquire the Project Team” Process
285.
Complex and large
projects would be more effectively managed in “Strong” and ‘Projectized” Structure
286.
If Changes are well
defined, its Fixed Price Contract but if they are not then its T & M.
287.
Punitive Damages are the damages intended to punish the wrong
doer
288.
“Utility Theory”
considers the pains or tolerance level a stakeholder has to risk
289.
There are three key components to a Risk
o Risk Event (The Event)
o Probability of the Event
o Impact or Effects of the Event (Amount at Stake)
o Risk Event (The Event)
o Probability of the Event
o Impact or Effects of the Event (Amount at Stake)
290.
Delhi technique is a “Consensus Technique”
291.
Residual Risk are those that “Remain” after Risk Responses
have been taken
292.
Inputs to Performance Reporting are
o Work Performance Information
o Performance Measurements
o Forecasted Completion
o QC Measurement
o Project Plan
o Approved Change Requests and
o Deliverables
o Work Performance Information
o Performance Measurements
o Forecasted Completion
o QC Measurement
o Project Plan
o Approved Change Requests and
o Deliverables
293.
Interpersonal
communication takes three
forms
o Verbal
o Non-verbal and
o Written
o Verbal
o Non-verbal and
o Written
294.
When distributing information, the total message impact from the sender is
1.
7% words ,
2.
38% vocal tones and
3.
55% body language
295.
A ‘Planning Package”
is a WBS component below the control account but above the work
package. It is used for planning unknown work content that does not have detailed schedule activities
package. It is used for planning unknown work content that does not have detailed schedule activities
296.
There are two types of “Decision Models” that can be used for Project Selection during
the initiation Process
o Comparative (Benefit measurement Rating) Models
o Constrained (Mathematical Decision Models)
o Comparative (Benefit measurement Rating) Models
o Constrained (Mathematical Decision Models)
297.
Comparative (Benefit
measurement Rating) Models
o Decision Tree
o Criteria Profiling
o Weighted Factor
o Q-Sorting
o Delphi Technique
o Decision Tree
o Criteria Profiling
o Weighted Factor
o Q-Sorting
o Delphi Technique
298.
Constrained
(Mathematical Decision Models)
o Logical Framework Analysis
o Linear Program Programming
o Logical Framework Analysis
o Linear Program Programming
299.
The “Control Points” in the WBS used for isolated assignment to work centers are
referred to as the “Control Account Plan”
300.
Control account Plan
(CAP) is a management
control point where the integration of scope,
budget and schedule take place and where the measurement of performance takes place.
These CAPS are placed at the selected management points in the WBS.
budget and schedule take place and where the measurement of performance takes place.
These CAPS are placed at the selected management points in the WBS.
301.
Cost Estimates include
All Resources to be charged to the Project
302.
A Control Account is a management control point that can be placed at
selected management points of the WBS above the Work Package Level ( Like RTN)
303.
To convey information
between two or more parties, the communication process must have a medium.
The three most common
media are
o Visual
o Auditory and
o Tactile
o Visual
o Auditory and
o Tactile
304.
Four steps of
performing RCA (Root Cause
Analysis) are
o Data Collection
o Casual Factor Charting
o Root Cause Identification
o Recommendation Generating and Implementation
o Data Collection
o Casual Factor Charting
o Root Cause Identification
o Recommendation Generating and Implementation
305.
Scatter Diagrams are used to investigate the possible
relationship between two variables that both relate to the same “EVENT”
306.
BCR (Benefit Cost Ratio) compares the
benefits to the costs of the project where the Benefits are the same as
Revenues or often referred to as the “Payback period”
307.
Payback Period
Number of years required for an organization
to recapture an initial investment.
Discount rate is not taken into account in
calculations for payback period.
Project Selection Criterion: Select a project
with lower payback period.
Example: There are two projects. Project A has
an investment of $500,000 and a payback period of 3 years. Project B has an
investment of $300,000 and a payback period of 5 years. Using the payback
period criterion, which project will you select?
Answer: Project A will be selected. The fact
that project B has a smaller investment than project A will not impact the
selection.
308.
Project performance is
impacted by Four Basic Cultures
o World
o National
o Business and
o Leadership
o World
o National
o Business and
o Leadership
309.
When one considers
their Culture to be superior, they are called “Ethnocentric”
310.
Use of personal space
during social interaction is known as “Proxemics”
311.
Risk is the notion of dealing with “Uncertainty”
o Knows at the extreme end of the Uncertainty Spectrum will definitely affect you, although you have no control over them
o Knows-Unknowns are items that will affect you although you are not able to predict how or how much they will effect you
o Unknown – Unknowns are items or situations whose existence we cannot imagine (Who knows?)
o Knows at the extreme end of the Uncertainty Spectrum will definitely affect you, although you have no control over them
o Knows-Unknowns are items that will affect you although you are not able to predict how or how much they will effect you
o Unknown – Unknowns are items or situations whose existence we cannot imagine (Who knows?)
312.
Residual risks are those risks that remain after risk responses have been
implemented. Residual risks are expected to remain after
planned responses have been taken, as well as those that have been deliberately
accepted.
313.
A Records Management
Systems is a specific set of processes, related control functions and
automation tools used by the PM to manage contract documentation and records.
Its the TT of Contract Administration Process
314.
Parametric (Top –
Down) uses historical data and statistical relationships to determine costs
315.
Constructive team
roles include
Initiators, Information seekers, Information givers,
Encouragers, Clarifiers, Harmonizers, Summarizers and Gate Keepers
Encouragers, Clarifiers, Harmonizers, Summarizers and Gate Keepers
316.
Destructive team roles include Aggressor, Withdrawer, Blocker,
Devil’s advocate, Recognizer, Topic Jumper and Dominator
317.
“To Complete
Performance Indicator” (TCPI) determines the cost performance efficiency
required to complete the project within the original budget (BAC) or revised budget (EAC);
required to complete the project within the original budget (BAC) or revised budget (EAC);
318.
TCPI > 1 is NOT
good; To calculate TCPI, take the value of the work remaining over the value of
funds remaining
319.
CPI and SPI must be
Equal or greater than 1.
320.
“Eustress” is a stress
that will motivate and contribute to an increase in performance
321.
Quantitative based
durations (Parametric technique) multiply a known element, like lines of code
required by the time it takes to develop one line of code. The result is the
total estimate for the activity
322.
Quality Metrics are the Outputs of Quality Planning. It
is an operation definition that describes “what” something is and “how” it will
be measured in very specific terms
323.
Straight-line
depreciation is the simplest method
of depreciating an asset and is frequently utilized on a project to determine
its economic feasibility. Straight-line depreciation is a method that divides
an asset’s cost and its expected salvage value by its expected utilization
period
324.
Performance Reporting is an INPUT to all “Control” Process
(Except Quality Control)
325.
Decision Trees are considered Quantitative while Influence diagram are considered Qualitative.
326.
Influence diagram shows the dependencies among the
variables more clearly than the decision tree
327.
A “Bill of Material” (BOM) describes the product in terms of its assemblies,
sub-assemblies and basic parts
328.
Allowing “Automatic Approval” of changes is a function of the Change
Control System and NOT Configuration Management
329.
Contingency Plan document outlines the actions to be taken if
an identified risk event should occur
330.
Variable and attribute
sampling are forms of
acceptance sampling.
Variable sampling evaluates a characteristic measured on a numerical scale
Attribute sampling tests for defective or non defective
Variable sampling evaluates a characteristic measured on a numerical scale
Attribute sampling tests for defective or non defective
331.
Parametric
Modeling applies to only
Project with Similar characteristics
332.
The point of total assumption (PTA) is a price determined by a fixed price
plus incentive fee contract (FPIF) above which the seller bears all the loss of
a cost overrun. It is also known as the "most pessimistic cost
PTA = ((Ceiling Price - Target Price)/buyer's Share Ratio) +
Target Cost
333.
Variance analysis involves comparing actual project
results to planned or expected results
334.
Trend analysis involves examining project results over
time to determine if performance is
improving
improving
335.
Arrow diagramming method (ADM) is a network diagramming technique in which activities are
represented by arrows.[1] ADM is also known as the activity-on-arrow (AOA) method. ADM only shows finish-to-start relationships,
meaning that each activity is completed before the successor activity starts.
336.
Senior
Management is responsible for issuing the charter.
337.
Insurance is an example of transferring risk.
338.
Grade refers to category or rank given to entities having same
functional use but different technical characteristics. As an example a basic
$10K car belongs to a different grade when compared to a $50K luxury car. Your
expectations from the two cars and their performances will differ because they
belong to different grades. Hence, Bad grade is acceptable, but bad quality is not.
339.
PDCA (plan–do–check–act or plan–do–check–adjust)
The Plan-Do-Check-Act
cycle is a way of making small improvements and testing their impact before you
make a change to the process as a whole. It comes from W. Edwards Deming's work
in process improvement, which popularized the cycle that was originally
invented by Walter Shewhart in the 1930s.
340.
Seven Basic Tools of
Quality is a designation given to a fixed set of graphical techniques
identified as being most helpful in troubleshooting issues related to quality.[1] They are called basic because they are suitable for people
with little formal training in statistics and because they can be used to solve
the vast majority of quality-related issues.
FiSH-P-CCC
The seven tools are:
341.
To find out which
issue has Maximum Impact – Use Pareto Diagram
342.
Potential causes of a
problem can be looked by creative way to analyze quality – Fishbone
Diagram/Ishikawa.
343.
Project managers must
have a “zero tolerance” policy on racist
remarks, or any other cultural insensitivity. If there is an incident
involving racism, sexism or any other kind of discrimination, your top priority
is to correct that. Every company has a policy that guides how you handle this
kind of situation, so a question involving racism will usually involve the
company's policy or HR department.
344.
Just remember, lessons
learned are your most important organizational process assets.
345.
Job security, salary, clean and safe working conditions are
examples of hygiene factors. Appreciation at work is not a hygiene
factor, but instead a motivating factor.
346.
Maslow’s Hierarchy of
Needs:
347.
Dynamic Programming is an example of Constrained
Optimization method. Murder board is an example of benefit measurement method.
348.
Benefit Measurement Method
- Most Common project
selection approach, it is a comparative approach, uses scoring models, cost
benefit analysis, review board, economic models.
349.
What are some examples
of the Benefit Method Model - Return
or Investment (ROI), Net Present Value (NPV), Payback Period, Expected Present
Value, Internal Rate of Return (IRR)
350.
Constrained Optimization
Method - Uses a mathematical
approach for project selection by using, decision tree models, applies a risk
element to get an Expected Monetary Value, and uses linear programming,
nonlinear programming, dynamic programming, and multi-objective programming.
351.
Which selection model
utilizes ROI - Benefit Measurement Model
352.
Who is responsible for performing Scope Validation? - Customer (Control
Scope process is part of scope management knowledge area.)
353.
In oligopoly, the action of one seller has an impact on
other sellers, as there are very few sellers.
354.
Crashing involves adding extra resources to reduce the
project duration.
355.
A risk trigger is an indication
that the risk is about to occur or has occurred.
356.
Lag is the amount of time after the completion
of the predecessor activity, when the successor activity can start.
357.
According to PMBOK 90% of
Project Managers time is spent in communicating.
358.
According to PMI, Compromise is an example of a
loose-loose situation.
359.
A CPI of greater than one indicates you are taking less money than planned to do the
project.
360.
Ethnocentrism refers
to belief that one’s culture is superior to other cultures.
361.
Stakeholder Management is
about the creation and maintenance of
relationships between the project team and stakeholders. Under specific
circumstances, answers B and C may be partially or. Answer D is incorrect: what
is created as the stakeholder management plan, not the stakeholder management
strategy. PMBOK® Guide, 5th edition, p. 400
362.
Tornado Diagram – Sensitivity analysis – Perform Quantitative Risk Analysis process
363.
Project Scope the work needed to complete a product, service, or result
364.
Inspection is a scope validation technique that
includes activities (such as measuring, examining, and verifying) to determine
whether work and deliverables meet requirements and product acceptance
criteria. [PMBOK 5th edition, Page 135]
365.
Midway through the Collect
Requirements process, a project manager finds that there are many unresolved
issues. Which of the following is usually the best way to discover and resolve
issues? – Facilitated Workshops.
366.
Facilitated
Workshops also called as Joint Application Design ( JAD Session)
367.
Activity duration
estimates
are quantitative assessments of the likely work periods to complete an
activity. They do not contain any lag or lead information.
[PMBOK 5th edition, Page 172]
368.
Cost Performance Index (CPI) of more than 1.0 indicates the project is under
budget.
369.
The Work Breakdown
Structure (WBS) provides the framework for the cost management plan. The WBS
contains control accounts, which link directly to the performing organization's
accounting system. [PMBOK 5th edition, Page 199]
370.
The grade of a product
relates to the technical characteristics of the product. [PMBOK 5th edition, Pg
228]
371.
(PDPC) Process decision program
charts - useful method for contingency planning, by
helping a team anticipate intermediate steps that could derail achievement of a
project goal.
372.
Prioritization matrices are an important quality planning tool. They provide a way
to rank a diverse set of problems and issues by order of importance are usually generated through brainstorming.
373.
Mind Mapping – Affinity diagrams
374.
Business partners are External
Organizations.
375.
Six-phase decision-making model, the project
manager first defines the problem. Then he or she generates solutions, puts
ideas into action, plans the solution action and plans the solution evaluation.
Once the solution is implemented, he or she evaluates the outcome and process.
Therefore, all choices except for problem solution escalation are part of this
model. [PMBOK 5th edition, Page 516]
376.
Smoothing is a temporary way to resolve conflict.
377.
Conflict is inevitable in
a project environment.
378.
A key project in an
organization has been ignored, due to high travel expenses associated with the
movement of subject matter experts and other specialists across various project
locations. Which of the following will permit such a project to be undertaken
in a cost-efficient manner? – Virtual Teams
379.
E-mail
messages are normally considered informal written communication. E-mail is a
written form of communication. Another example of informal written
communication is memorandums
380.
Whenever contracts are involved in a project,
the project manager and team should use formal written communication methods.
[PMBOK 5th edition, Page 287]
381.
A contract is a mutually binding agreement that obligates the seller to provide the
specified product, or service or product and obligates the buyer to pay for it.
382.
The online database is an example of a
Project Management Information System. [PMBOK 5th edition, Page 554]
383.
The project deliverables are not part of the
project file. Documentation resulting from Project’s activities – all plans,
PMPLAN, etc..
384.
project competing constraint’s - Six
competing project constraints are scope, quality, schedule, budget, resources
and risk. Therefore, PROCUREMENT is NOT
project competing constraint
385.
Expected Monetary Value = Probability * Impact
386.
A point in time that a project or project phase is authorized to its
completion is called a project boundary.
387.
A point in time that a project or project phase is authorized to its
completion is called a project boundary.
388.
The best choice of action for the project
manager in this situation if Stakeholder missed is brought up by
a team member then authenticate the information before taking any action or
include the stakeholder.
389.
One of the mandatory standards in the PMI Code of Ethics and Professional Conduct
is respect. A project manager must
listen to others’ points of view and understand them. However, before asking
the junior project manager for evidence of his or her PMP certification, you
must ask your functional manager to provide evidence to support his or her
allegations. You can suspend the junior project manager or report him or her to
PMI if there sufficient evidence of his or her guilt. [PMI Code of Ethics and
Professional Responsibility, Page 3]
390.
What should you do as a senior project manager if the PMP certification claimed by a recently recruited project manager doesnot appears in the PMI website?
Correct Response: Reason
Request more information from the new recruit
391.
A point in time that a project or project phase is authorized to its
completion is called a project boundary.
392.
Iterative Relationship is best suited for
Uncertain Conditions.
393.
Identification of new risks, reassessment of old risks, and closing of outdated risks are done as part of the Control Risks
phase. How often should project risk reassessment be scheduled?
393.Answer:
It depends on the project processes
relative to its objective!
394.
Statistical sampling will provide sufficient inspection to ensure a
high likelihood of a quality product while saving money for theproject. [PMBOK 5th edition, Page 240]
395.
Hammock Activity = Summary Activity
396.
A Probability and Impact Matrix contains risks prioritized according to their potential implications for meeting the project's
objectives. The typical approach is: Lookup Table or
Probability & Impact matrix.
397.
Facilitator
is a Management Skill
398.
Acceptance
Criteria is done in Define Scope.
399.
A critical
resource is on another project team. It is essential that you get his time for
your project. You have contacted the resource’s team manager several times but
have received a poor response. What should you consider doing next?
Contacting the
manager once again will not help since you have already had a poor response.
The best option is to try using management influence to obtain the resource's
time for your project. Should all efforts to obtain the resource prove
unsuccessful, alternatives include planning for an alternate resource or
training another resource. [PMBOK 5th edition, Page 268]
400.
The completion of project scope is measured against the project management
plan, whereas the completion of
product scope is measured against the product requirements. The work of the
project results in delivery of the specified product scope. [PMBOK 5th edition,
Page 106]
401.
One of the most common
sources of confusion is the difference between a project stakeholder and a key
stakeholder. Who are the key stakeholders? the key
stakeholders are the subset of the project stakeholders that are in a decision making position\
402.
In the Conduct
Procurements process, sellers are selected and procurement contracts are
awarded to them. Contracts can be awarded in the form of a purchase order.
Since the PMO selected you to write the purchase order, it is in the process of
conducting procurements. [PMBOK 5th edition, Page 371]
403.
Earned value analysis is used as a trend analysis technique for monitoring
overall project performance. [PMBOK 5th edition, Page 352]
404.
Resource pooling - a large
number of simultaneously performed projects utilize the same groups of human
and other resources.
405.
If the tasks are not on the critical path of the
project, we cannot determine the PERT
estimate for the duration of the project. The PERT estimate can only be
calculated for the critical path of the project.
406.
Inspection
includes activities such as measuring, examining, and validating to determine
whether work and deliverables meet requirements and product acceptance
criteria.
407.
Dependency
Determination is a tool/technique for the Sequence Activities process. None of
the other options are tools or techniques for this process.
408.
Management
by objectives is a systems approach for aligning project goals with organizational
goals, project goals with the goals of other subunits of the organization, and
project goals with individual goals.
409.
Unresolved
issues can be a major source of conflict and project delays.
410.
Herzberg’s Motivation-Hygiene Theory
Herzberg's
findings revealed that certain characteristics of a job are consistently
related to job satisfaction, while different factors are associated with job
dissatisfaction. These are:
Factors
for Satisfaction
|
Factors
for Dissatisfaction
|
Achievement
Recognition
The
work itself
Responsibility
Advancement
Growth
|
Company
policies
Supervision
Relationship
with supervisor and peers
Work
conditions
Salary
Status
Security
|
411.
When a project deviates significantly from
the baseline, updated
risk identification and analysis
should be performed.
412.
The project manager usually follows
different leadership styles as listed below:
• Autocratic: Makes decisions himself/herself; allows team members little involvement and discussion before a decision is made.
• Directing: Instruct people what tasks will be performed and when and how they should be performed.
• Laissez Faire: Does not interfere; team is left unsupervised which may lead to anarchy.
• Democratic: Allows team to discuss issues and reach decisions, although still guides and advises.
• Delegating: Delegates to team members, particularly if competent to handle tasks.
• Coaching: Issues instructions and then supports and monitors.
• Discussing: Two-way communication and discussion with team members.
• Facilitating: Coordinates inputs from several sources before making a decision.
• Supportive: Provides positive assistance and encouragement; maintains and presents a positive outlook during times of uncertainty; listens and encourages.
• Participatory: Involve others; same as Democratic style.
• Task-Oriented: Enforces task completion by deadlines.
• Team-Based: Emphasizes teamwork and working well together.
• Assertive: Confronts issues and displays confidence; establishes authority with respect.
• Autocratic: Makes decisions himself/herself; allows team members little involvement and discussion before a decision is made.
• Directing: Instruct people what tasks will be performed and when and how they should be performed.
• Laissez Faire: Does not interfere; team is left unsupervised which may lead to anarchy.
• Democratic: Allows team to discuss issues and reach decisions, although still guides and advises.
• Delegating: Delegates to team members, particularly if competent to handle tasks.
• Coaching: Issues instructions and then supports and monitors.
• Discussing: Two-way communication and discussion with team members.
• Facilitating: Coordinates inputs from several sources before making a decision.
• Supportive: Provides positive assistance and encouragement; maintains and presents a positive outlook during times of uncertainty; listens and encourages.
• Participatory: Involve others; same as Democratic style.
• Task-Oriented: Enforces task completion by deadlines.
• Team-Based: Emphasizes teamwork and working well together.
• Assertive: Confronts issues and displays confidence; establishes authority with respect.
413.
Team uses
a set of rigorous scripts to test the code and functionality. In which process
would the team use these scripts to test the modules and in what process would
the test scripts be audited to ensure they are valid and produce the desired
results?
414.
Control Quality is the process of monitoring
and recording results from the project to assess/measure performance and
recommend any changes. Deliverables are also inspected and checked to ensure
there are no defects.
415.
Auditing is a key tool of Perform Quality
Assurance.
416.
Earned value analysis is used as a trend
analysis technique for monitoring overall project performance. [PMBOK 5th
edition, Page 352]
417.
In your project, you actively manage stakeholder’s
engagement in order to meet their needs and expectations. Doing this is very
beneficial, however, it may not help to:
Choice 1 Increase the likelihood of stakeholders` acceptance of
the project goals
Choice 2 Influence and negotiate expectations of stakeholders to
achieve project goals
Choice 3 Ensure stakeholders` awareness of all project details
Choice 4 Uncover and discuss stakeholder issues and concerns
Correct
Choice: 3
Justification: Manage Stakeholder Engagement
involves communicating and working with project stakeholders to meet their
needs and expectations. Actively managing the expectations and engagement of
stakeholders should increase the likelihood of project acceptance and support,
and should also minimize stakeholder resistance. This process also involves
negotiating and influencing stakeholders in favor of achieving the project
goals. Addressing concerns that have not yet become issues and anticipating
future problems is useful for managing project risks. Doing all this however,
does not ensure that stakeholders are fully aware when they should be, and in
fact, it is not always desirable for stakeholders to be aware of ALL project
details.
Option 3 (i.e., Ensure stakeholders`
awareness of all project details) is not recommended. The project manager
should try to manage information, so that only appropriate and relevant
information reaches the appropriate stakeholders.
418.
Which of the following statements about
Control Quality is accurate?
A. Prevention refers to keeping errors out of
the process, whereas inspection refers to keeping errors out of the hands of
the customer.
B. Attribute sampling determines whether the
result conforms or not, and variables sampling determines the degree of
conformity.
C. Tolerances refer to a specified range of
accepted results and control limits refer to thresholds, which can indicate
whether the process is out of control.
D. Control Quality is only performed during
the Monitoring and Controlling phase of a project.
Choice 1 B, C and D
Choice 2 A, C and D
Choice 3 A, B and D
Choice 4 A, B and C
Correct
Choice: 4
Justification
: Cost control should be used during the project executing and closing phases
to formally demonstrate, with reliable data, that the sponsor and/or customer`s
acceptance criteria have been met.
419.
You are creating a cost management plan for
your Six-Sigma project. In this context, which of the following statements
relating to creation of the cost management plan is inaccurate?
Choice 1 Specifies
the precision level to which the schedule activity cost estimates will adhere
Choice 2 Establishes
variance thresholds for costs
Choice 3 Defines
formats for various cost reports
Choice 4 Uses
preferred tools for cost estimating
Correct Choice: 4
Justification : Cost management plan does not
include cost estimation, i.e., tools for cost estimating are not used for
creation of cost management plan. These tools will be used in the Estimate
Costs process.
PMP
Formulas:
1. PERT
|
(P + 4M + O )/ 6 Pessimistic, Most Likely,
Optimistic
|
2. Standard Deviation
|
(P - O) / 6
|
3. Variance
|
[(P - O)/6 ]squared
|
4. Float or Slack
|
LS-ES and LF-EF
|
5. Cost Variance
|
EV - AC
|
6. Schedule Variance
|
EV - PV
|
7. Cost Perf. Index
|
EV / AC
|
8. Sched. Perf. Index
|
EV / PV
|
9. Est. At Completion (EAC)
|
BAC / CPI,
AC + ETC -- Initial Estimates are flawed
AC + BAC - EV -- Future variance are Atypical
AC + (BAC - EV) / CPI -- Future Variance would
be typical
|
10. Est. To Complete
Percentage complete
|
EAC - AC
EV/ BAC
|
11. Var. At Completion
|
BAC - EAC
|
12. To Complete Performance IndexTCPI
|
Values for the TCPI index of less then 1.0 is
good because it indicates the efficiency to complete is less than planned.
How efficient must the project team be to complete the remaining work with
the remaining money?
( BAC - EV ) / ( BAC - AC )
|
13. Net Present Value
|
Bigger is better (NPV)
|
14. Present Value PV
|
FV / (1 + r)^n
|
15. Internal Rate of Return
|
Bigger is better (IRR)
|
16. Benefit Cost Ratio
|
Bigger is better ((BCR or Benefit / Cost)
revenue or payback VS. cost)
|
17. Payback Period
|
Less is better
Net Investment / Avg. Annual cash flow.
|
18. Expected Monetary Value
|
Probability * Impact
|
19. Point of Total Assumption (PTA)
|
((Ceiling Price - Target Price)/buyer's Share
Ratio) + Target Cost
|
20. Sigma σ
|
|
grateful summarization
ReplyDeleteThanks for the helpfull summary. Do the colors (of the arrows and blocks) mean anything in your inputs and outputs slides?
ReplyDeleteSorry for late response!
ReplyDeleteYes those where high potential on exam :)
Betway review - JTM Hub
ReplyDeleteOur experts 목포 출장마사지 have been around 세종특별자치 출장샵 for 의왕 출장안마 betting, but it's not really a sportsbook, casino, poker, and sports 여주 출장마사지 betting. Betway Sportsbook App. Betway Mobile App. 속초 출장안마 Betway Casino App. Betway